Short production runs have what effect on the amount of average WIP held?


A) Increased amount of WIP
B) Decreased amount of WIP
C) No change to amount of WIP
D) It is impossible to determine the effect of short production runs on the amount of WIP

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB) . J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average flow time of these jobs?


A) 0
B) 7
C) 14
D) Cannot be determined from the information given

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

Input and output control refers to?


A) Quality assurance of materials and completed goods
B) Management of input and output production flow rates
C) Proper training of employees for customer service
D) Handling of customer service calls at a call center

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

The ability to produce a wide variety of product types is referred to as?


A) Production mapping
B) Production prowess
C) Production flexibility
D) Production differentiation

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

Which job shop dispatch rule tends to work well to minimize average flow time?


A) CR
B) SPT
C) EDD
D) FCFS

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

The orders of some important customers may be?


A) Given processing priority
B) Intentionally delayed
C) Refused
D) Placed at the end of the order queue

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

What type of chart is often used for forward scheduling?


A) Gary
B) Gravity
C) Garage
D) Gantt

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Customer orders, in a flow management context, are often referred to as jobs.

A) True
B) False

Correct Answer

verifed

verified

If I is the input rate and O is the output rate, what happens when I < O?


A) WIP decreases
B) WIP increases
C) WIP remains constant
D) I and O are not related to the WIP

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

A

Having high quality schedules for delivery vehicles can lead to?


A) Lower in-transit inventories
B) More on-time deliveries
C) Both lower in-transit inventories and more on-time deliveries
D) Neither lower in-transit inventories nor more on-time deliveries

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

Short production run tend to result in _________ machine setups.

Correct Answer

verifed

verified

Scheduling jobs into the future based upon job arrival date refers to?


A) Backward scheduling
B) Forward scheduling
C) Inverse scheduling
D) Advance scheduling

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

B

Shorter production runs tend to decrease production flexibility.

A) True
B) False

Correct Answer

verifed

verified

What type of rules determine which job to process next from a queue of waiting jobs?


A) Delivery
B) Distance
C) Dispatch
D) Distribution

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB) . J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average queue time of these jobs?


A) 0
B) 1
C) 2
D) Cannot be determined from the information given

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Two jobs (J1 and J2) are to be scheduled on a single workcenter. J1 has a process time of 5 and J2 has a process time of 3. J1 has a due date of time 6 and J2 has a due date of time 7. If the jobs are scheduled by the EDD rule, in what order will they be processed?


A) J2 then J1
B) J1 then J2
C) Random order
D) The EDD rule is not related to processing order

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Which job shop dispatch rule schedules the job with the shortest process time first?


A) CR
B) SPT
C) EDD
D) FCFS

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

Describe the challenges faced when scheduling jobs in a product-focused production system.

Correct Answer

verifed

verified

A successful answer should indicate the challenges such as keeping goods flowing through the system smoothly and maintaining a high degree of labor utilization.

The average of flow time minus processing time is?


A) Makespan
B) Average flow time
C) Average job tardiness
D) Average queue time

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

The primary scheduling issue in a product-focused facility is?


A) Fixed model sequencing
B) Constant model sequencing
C) Production model sequencing
D) Mixed model sequencing

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified