MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -Project managers typically perform four main tasks. Identify these and explain what they are.

Correct Answer

verifed

verified

• Project planning includes identifying ...

View Answer

When tasks must be completed one after another, they are called concurrent tasks.

A) True
B) False

Correct Answer

verifed

verified

  -A(n) ____________________ is a series of tasks with no slack time. -A(n) ____________________ is a series of tasks with no slack time.

Correct Answer

verifed

verified

  -A project is based on a pattern of ____________________. -A project is based on a pattern of ____________________.

Correct Answer

verifed

verified

A ____ might involve maximums for one or more resources.


A) successor task
B) task group
C) constraint
D) bottom-up technique

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

_____ is a full-featured program that holds the dominant share of the project management software market.


A) Apptivo
B) GanttProject
C) Microsoft Project
D) OpenProject

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Project management is dynamic and challenging, regardless of which software you use..

A) True
B) False

Correct Answer

verifed

verified

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -PERT/CPM is an example.

Correct Answer

verifed

verified

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -A condition, restriction, or requirement that the system must satisfy.

Correct Answer

verifed

verified

  -Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure. -Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure.

Correct Answer

verifed

verified

In any project, large or small, tasks depend on each other and must be performed in a sequence.

A) True
B) False

Correct Answer

verifed

verified

When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks.


A) descendent
B) successor
C) children
D) antecedent

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.


A) vital
B) baseline
C) foundational
D) critical

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Critical time is the amount of time that a task would be late without pushing back the completion date of the entire project. _________________________

A) True
B) False

Correct Answer

verifed

verified

Structured walk-throughs take place throughout the SDLC and are called ____ reviews, depending on the phase in which they occur.


A) technical
B) code
C) design
D) testing

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

  -When estimating the duration of a task, the project manager makes three time estimates for the task and then assigns a(n) ____________________, which is an importance value, to each estimate. -When estimating the duration of a task, the project manager makes three time estimates for the task and then assigns a(n) ____________________, which is an importance value, to each estimate.

Correct Answer

verifed

verified

MATCHING Identify the letter of the choice that best matches the phrase or definition. a.project management f.weight b.project coordinator g.bottom-up technique c.project leader h.dependent d.milestone i.concurrent e.constraint j.predecessor -What would a basic list of risk management steps include?

Correct Answer

verifed

verified

• Develop a risk management plan. A risk...

View Answer

For a project manager, reporting _____.


A) involves controlling capital
B) includes informing management, users, and the project team about the progress of the project
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs

E) C) and D)
F) A) and D)

Correct Answer

verifed

verified

  -The PERT chart called a network diagram in the accompanying figure represents a bottom-up technique, because it analyzes a large, complex project as a series of individual ____________________. -The PERT chart called a network diagram in the accompanying figure represents a bottom-up technique, because it analyzes a large, complex project as a series of individual ____________________.

Correct Answer

verifed

verified

____ is a possible cause of cost overruns related to human resource issues.


A) unrealistic estimates
B) poor monitoring of progress
C) inaccurate TCO forecast
D) turnover

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Showing 41 - 60 of 112

Related Exams

Show Answer